If you are comparing homes off West Washington Street, the most useful landmark is Holt Road. East of Holt, IndyGo's Blue Line will run down the middle of Washington Street. West of Holt, the buses turn north to Interstate 70 and head to the airport, and the stretch of Washington Street toward I-465 and the Hendricks County line is on a separate city schedule. Both halves are getting public money. The difference is what kind of money, what it pays for, and the year it shows up.
A house two blocks east of Holt and a house two blocks west of it share a street name. Over the next few years, they will see different construction, on different dates, paid for out of different budgets. Here is the corridor, block by block, as it stands in late November 2026.
The line that was planned, and the line being built
IndyGo first drew the Blue Line along Washington Street all the way from Cumberland to Indianapolis International Airport. In 2022, cost estimates came in $300 million over budget. As IBJ reported that December, the agency moved the route off West Washington at Holt Road and onto an express run along I-70. That change cut the last seven stations planned for West Washington.
The line that broke ground in early 2025 is the redesigned version. IBJ covered the ceremony for what it called the planned $378 million Blue Line, a 24-mile route from the airport to Cumberland. Most of the budget comes from federal grants. IndyGo's project page still describes the route as running from the airport via I-70, Holt Road and Washington Street, with service targeted for late 2028.
IndyGo's April 2024 design document lists the west-side stations heading east from the interstate: Washington Street at Holt Road, Central Green Boulevard, Belleview Place, Belmont Avenue and Harding Street, then South White River Parkway at the Zoo. The Holt Road station is the westernmost stop on Washington Street itself. For a homebuyer, that is the real map.
East of Holt: the money is already in the ground
The stretch from Holt Road to the river is where the Blue Line is most concrete, in both senses. In September 2025, Mirror Indy reported storm sewer work and temporary lane closures on Washington Street between Belmont and Harding. IndyGo's construction page, updated this month, shows active work around the future Belmont Avenue and Harding Street stations. It also shows the Holt Road to Rockville Road section of Washington Street scheduled from late 2026 through 2028, with utility relocation going first.
If you buy near those stations this winter, you buy into two more years of construction before the first bus runs. The construction is visible and funded, though, and the end date has held at 2028 through the closures IndyGo has reported.
The largest change on this side of Holt has nothing to do with buses. In August 2025, the state sold 56 acres of the former GM stamping plant site to Elanco for $27 million. Indiana Capital Chronicle reported that a broader One Health district could eventually include research, offices, housing, retail and green space. Elanco opened its new global headquarters there in October 2025. IPM News described it as the cornerstone of the OneHealth Innovation District. Longtime west-siders will remember the earlier $1.4 billion Waterside proposal for the same ground. The developer, Ambrose, dropped it in 2019, and the Elanco campus is what replaced it.
Housing developers have also lined up around the station areas. Radiant CDC lists The Plaza at Central Greens, 122 units of mixed-use affordable family housing, as transit-oriented development on the Route 8 and Blue Line corridor. Woda Cooper has proposed Richardson Townhomes & Flats at 50 N. Tibbs Ave., with 40 townhomes and 136 apartments, and IBJ reported that construction depended on tax credits. Farther south, the West Indianapolis Development Corporation's WestPark plan at 2302 W. Morris St. calls for 40 apartments, six for-sale townhomes and five single-family homes. Its posted timeline shows a groundbreaking in late 2026 and lease-up in early 2028.
West of Holt: a different kind of investment, on a later clock
When the route changed in 2022, the city stepped in for the stretch the Blue Line would no longer reach. IBJ reported a $20 million commitment for stormwater, sidewalk and drainage upgrades on West Washington Street, plus resurfacing in Fleming Gardens, with construction then expected to begin in 2025.
The city's current major projects list carries it as project ST-30-054, Washington Street rehabilitation from Lynhurst Drive to Holt Road. The scope is streets, sidewalks, curbs, traffic signals and drainage, and the timeline is Q2 2027 through Q3 2029. For planning, use the 2027 start date the city lists now.
That project counts for more than its price suggests. Before the reroute, Rick Proctor, former president of the West Side Chamber of Commerce, told IBJ that the corridor lacked sidewalks and that bus riders there had no choice but to walk it anyway. Sidewalks, curbs and drainage are the kind of street-level improvement a household notices every day, whether or not anyone in it rides the bus. Route 8, the regular bus along West Washington, carried 63,800 riders in October 2022, second only to the Red Line, according to the same IBJ story.
Past I-465, the longer-range picture comes from Develop Indy's West Washington plan, which IBJ covered in January 2024. It covers about 885 acres from the west side of I-465 to the Hendricks County line. Its Ben Davis Station concept includes more than 650 housing units, a 220-room hotel, and industrial, commercial and research space. The Bridgeport concept farther west includes a 115,000-square-foot multi-use facility, 100 to 200 homes and athletic fields. When the plan came out, the agency was in talks with three developers it did not name and had no finalized implementation timeline. For a buyer, those concepts describe what the city would like to see on that ground. They are not a schedule.
What transit has done elsewhere in Indianapolis
The Red Line is the closest local example, and the evidence from it is suggestive more than measured. In the 2022 IBJ story, Lacey Everett of the Metropolitan Indianapolis Board of Realtors said some buyers had paid more than asking price for property along the Red Line to get access to transit. She also said a long-term analysis would give the best read on property values. Mirror Indy reported that the Indy Chamber and Midtown Indy credited about $709 million across roughly 30 developments to the Red Line corridor. In 2025, the Indianapolis MPO announced plans to seek proposals for a Red Line After Study to measure changes since the line opened.
So development followed the Red Line, and some buyers paid for transit access. How much of a home's price comes from the bus line, as opposed to everything else changing in Midtown, has not been pinned down. A seller on West Washington who prices a home as if 2028 has already arrived is asking you to pay for something nobody has measured.
The October numbers give buyers time to sort this out
The wider market this fall gives you room to look at a corridor block by block instead of rushing. MIBOR's October 2026 report for its 17-county region shows a median single-family sale price of $310,000, down 1.6% from October 2025. Median days on market rose to 29 from 22 a year earlier, and supply rose to 3.3 months from 2.5. In Marion County, the Indiana REALTORS October report shows a $240,000 median, down 3% year over year, with 35 median days on market and 3.7 months of inventory.
ZIP-level figures for the west side vary widely, and they are best read as a backdrop rather than as a measure of transit's effect. In October 2026, ZIP code 46222 posted a $140,000 median on just 20 closed sales, with 3.7 months of inventory. ZIP 46214 posted a $245,000 median with 2.8 months of inventory. ZIP 46231, which runs out toward the Hendricks County line, posted $251,500 with 2.8 months. On 20 sales, one or two closings can move a monthly median by thousands of dollars. Compare specific homes against recent sales on the same streets.
The practical takeaway for a 2026 purchase on West Washington is the schedule that applies to the specific block. Near the Belmont, Harding and Central Green stations, that means funded transit construction now, service targeted for late 2028, and the Elanco campus already open nearby. Between Holt and Lynhurst, it means a street rebuild listed for 2027 through 2029. Beyond I-465, it means the Ben Davis Station and Bridgeport concepts, which had no finalized timeline when Develop Indy released them.
Quick Answers
When is the Blue Line expected to start running? IndyGo's current target is late 2028.
Will the Blue Line stop on Washington Street west of Holt Road? No. West of Holt Road, the route uses I-70 to reach the airport, and the Holt Road station is the westernmost stop on Washington Street.
What is planned for West Washington Street between Holt and Lynhurst? A city rehabilitation of streets, sidewalks, curbs, signals and drainage, listed for Q2 2027 through Q3 2029.
If you're weighing a home along West Washington Street, or deciding between the near west side and suburbs farther out like Avon, Home Strategy Group can go through the specific blocks with you, along with the construction schedule each one sits under and the recent sales on those streets. Request your personalized market consultation, and see our Indianapolis neighborhood page and buyer's guide to get started.